Introduction
The most common sizing mistake is adding up every nameplate on the site, adding a margin on top, and ordering that. It produces a transformer that spends its entire life lightly loaded — paying no-load losses around the clock for capacity that is never called on.
Start with measured demand, not nameplate
Connected load and maximum demand are different numbers, usually by a wide margin. If the site is already energised, a week of logged demand data from the existing meter is worth more than any calculation from a load schedule.
Then think about the shape of the load
- Flat, continuous load — load losses dominate; it is worth paying for lower-loss windings.
- Peaky, intermittent load — no-load losses dominate because the unit idles most of the time.
- Cyclic heavy duty — furnaces and similar; thermal cycling and short-circuit withstand are the main question.
Leave headroom deliberately, not reflexively
If expansion is a real plan with a date on it, size for it. If it is a vague possibility, size for today and keep the substation layout able to take a second unit later.
Check the fault level
Impedance is not a free variable — too low and downstream switchgear sees a fault level it cannot interrupt; too high and voltage regulation suffers.
What to send when you enquire
- Measured maximum demand, or a load schedule if the site is not built yet
- Rough duty pattern — shifts, cycles, seasonality
- Incoming and outgoing voltage
- Downstream switchgear fault rating
- Where the unit will physically stand, and the access route to get it there